30 June 2015

RP Energy cuts Subic power plant capacity target to 300 MW

THE Redondo Peninsula (RP) Energy Inc. is lowering by half the target capacity of its newest coal-fired power plant at the Subic Bay Freeport Zone in Zambales.

The consortium is set to change the project parameters to reduce the capacity from 600 megawatts (MW) to 300 MW, Meralco Chairman Manuel V. Pangilinan said.

RP Energy is a joint venture of Meralco PowerGen Corp., Aboitiz Power Corp., and Taiwan Cogeneration International Corp.
Pangilinan attributed the changes to the issues surrounding the transmission line connection.

“There were issues on the distance of the connection of the transmission line to the grid,” Pangilinan told reporters.

He explained that the transmission line from the power plant to the grid will have to go through areas that are apparently occupied by indigenous people.

“There are pockets where there are reserved areas. So you know we cannot build on top of that. That’s prohibited by law,” he said.

The project was originally conceived as 600 MW power facility, composed of two 300 MW coal­fired plant.

Its construction was delayed because of the Writ of Kalikasan filed before the Supreme Court (SC) by groups opposing the power plant.

The High Court upheld the project’s environmental compliance certificate, as well as the lease and development agreement with the Subic Bay Metropolitan Authority.

The project is now in the construction phase after the consortium has hired the engineering, procurement and construction contractor.
The consortium has tapped a group of local banks to help finance the project. The power plant is expected to contribute additional generating capacity to the Luzon grid. (Ritchie A. Horario, The Manila Times)

http://www.manilatimes.net/rp-energy-cuts-subic-power-plant-capacity-target-to-300-mw/195801/

04 February 2015

SC clears way for long-delayed Subic plant

THE SUPREME COURT finally cleared the way for a Meralco-led consortium to build its long-delayed 600-megawatt coal-fired power plant in Subic, Zambales.

In en banc session on Tuesday, justices voted 13-0 to uphold the validity of the coal power project of Redondo Peninsula Energy, Inc. (RP Energy) in Barangay Cawag.

The ruling upheld the validity of the environmental compliance certificates issued by the Department of Environment and Natural Resources (DENR) on December 2008 and July 2010. It also upheld the validity of the June 2010 Lease and Development Agreement with the Subic Bay Metropolitan Authority (SBMA).

Associate Justices Estela M. Perlas-Bernabe and Mario Victor “Marvic” F. Leonen voted in favor of RP Energy, but with qualifications, Supreme Court Public Information Office (PIO) Chief Theodore O. Te said in a briefing.

The high court also unanimously voted to deny the petition for writ of kalikasan filed by former Bayan Muna Rep. Teodoro A. Casiño and other individuals, as well as the organizations Advocates for Wildlife and Environment Protection, Wildlife in Need, Subic-Olongapo Cancer Foundation, Inc., and PAMALAKAYA (National Federation of Small Fisherfolk Organization in the Philippines).

Associate Justices Arturo D. Brion and Francis H. Jardeleza took no part in the voting, with the former being on leave and the latter inhibiting due to his previous involvement as Solicitor-General.

A full copy of the decision has yet to be issued.

The decision reversed the January 2013 ruling by the Court of Appeals invalidating the project’s amended environment compliance certificate (ECC) due to RP Energy’s failure to conduct a new environmental impact assessment.

The appellate court’s earlier decision was also based on the supposed lack of consent from the local government and the National Commission on Indigenous Peoples (NCIP) to support the Lease and Development Agreement with SBMA.

RP Energy is a joint venture of Meralco PowerGen Corp., Aboitiz Power Corp., and Taiwan Cogeneration International Corp..

The project was originally expected to go online by the this year’s dry season but development was halted because of the writ of kalikasan filed against the project.

The Supreme Court first released a resolution on the writ dated July 31, 2010, against Environment Secretary Ramon Jesus P. Paje, the Subic Bay Metropolitan Authority and RP Energy.

Such writs serve as a judicial remedy to protect against projects inflicting possible environmental damage that affects inhabitants.

The petitioners claimed RP Energy violated its environmental impact statement and environment compliance certificate (ECC).

The petitioners also claimed the ECC was issued without complying with the conditions of affected indigenous people and without prior approval of local government units.

While the project proponents have yet to receive their respective copies of the court’s decision, they welcomed the development saying this would help the energy industry.

“We have yet to read the decision. Assuming it’s all positive, then it’s good for the industry,” said Alfredo S. Panlilio, senior vice-president of Manila Electric Co., the parent firm of Meralco PowerGen.

Stephen G. Paradies, senior vice-president of Aboitiz Equity Ventures, Inc. (AEV), also said AboitizPower has yet to receive a formal copy of the decision.

AEV is the parent company of AboitizPower.

“We intend to pursue this project. It’s very good news,” said Mr. Paradies. (Claire-Ann M. C. Feliciano and Vince Alvic A. F. Nonato, BusinessWorld)

http://www.bworldonline.com/content.php?section=Economy&title=sc-clears-way-for-long-delayed-subic-plant&id=102060

06 June 2014

Meralco pushes forward reparations at Subic plant site

The Subic freeport zone is likely the final plant site for the planned 600-megawatt coal fired power facility being lead-developed by the power generation arm of Manila Electric Company (Meralco) – primarily when a pending court case on the project eventually clears up.

A document from Meralco has hinted that the Subic Bay Metropolitan Authority (SBMA) is set to ratify the Lease and Development Agreement (LDA) for the proposed plant site “to reflect additional terms.” No further details were provided.

It must be culled that the original LDA was declared invalid by the Court of Appeals (CA), alongside its ruling on a Writ of Kalikasan filed by groups opposing the project.

The petition was filed before the Supreme Court, but it was subsequently remanded to the CA for hearing on the merits of the case.

The proposed 600-megawatt power facility was initially targeted for commercial operation by 2015, and it could have placed Luzon grid on ‘safe ground’ versus the feared power interruptions especially during the high-demand months of summer.

The project is to be undertaken under corporate vehicle RP Energy. Meralco PowerGen is the majority equity holder, while its partners are Therma Power, Inc. of the Aboitiz group and Taiwan Cogeneration International Corporation.

On pre-construction activities, the Meralco document indicated that “RP Energy is proceeding with certain development activities that are not hampered by the SC proceedings.”

As of March this year, it was emphasized that “site preparation work is almost complete and RP Energy has commissioned its contractor to conduct preliminary engineering works on the power plant in order to reduce the overall construction period.”

An environmental compliance certificate (ECC) was already issued by the Department of Environment and Natural Resources (DENR) for the two blocks of 300-megawatt electricity generating units designed for the facility.

Full implementation, however, could not move forward until the legal hurdle of the pending Writ of Kalikasan is resolved by the courts.

While the appellate court has initially denied the Writ of Kalikasan petition, it conversely noted “certain deficiencies in the process of the DENR in its issuance of the original ECC for the 300MW coal-fired plant” which has also affected the LDA for the project site. (Myrna Velasco, Manila Bulletin)

http://www.mb.com.ph/meralco-pushes-forward-reparations-at-subic-plant-site/

23 May 2014

Power supply a challenge to investors

Power outages across the Philippines amid shutdowns at electricity plants and increasing summer demand are raising concern the country’s stunted generation capacity will stifle investment and economic growth.

Two of the Philippines’ three main islands are on “Red Alert” after supply fell below peak demand this week as aging facilities shut for repairs and temperatures rise to near 40 degrees Celsius (104 Fahrenheit). Delays in building new plants may slow the expansion of Asia’s second-fastest growing economy, according to Erramon Aboitiz, president of Aboitiz Power Corp., the nation’s second-largest utility.

“It’s time to worry,” Aboitiz said in an interview at the ASEAN Finance Ministers investor seminar in Manila on May 20. “Investors are always forward-looking and when they see projections of a potential power problem, they’ll decide to put their investments somewhere else.”

The strain this summer on power plants highlights how the Philippines’ under-performing electricity sector threatens the country’s economic growth, which is second only to China in the Asia-Pacific. Gross domestic product rose 7.2 percent in 2013 and is poised to remain among the world’s five fastest-expanding until 2016, according to economists surveyed by Bloomberg.

As the economy expands, so has the country’s demand for electricity. Consumption jumped 50 percent in the 10 years to 2012, more than three times the 16 percent growth rate over that same period for the nation’s generating capacity, according to government data.

Some new projects are being delayed because of environmental concerns, such as Aboitiz Power and Manila Electric Co.’s 600-megawatt coal-fired power plant at the Subic Freeport zone north of the capital, which was blocked by a court order. The companies in July 2011 said the first 300 megawatts of the plant will be available by 2014.

“The power crisis is going to be costly,” Ronald Mendoza, executive director of the Asian Institute of Management Policy Center in Manila, said in a telephone interview yesterday. “It will affect manufacturing and services, so there will be implications on production. Investors may scale back or delay investments.”

With peak power demand forecast to grow about 4 percent annually until 2030, the country will need more than 13,000 megawatts of additional capacity, or 80 percent more than what’s installed, according to Department of Energy data. The government estimates that will require 2.8 trillion pesos ($64 billion) of investment. About 1,800 megawatts of new generation has been committed so far.

The central Visayas region, home to the famous beaches of Boracay island, had zero power reserves yesterday. The southern Mindanao region is on a reserve deficit of nearly 100 megawatts, according to data from National Grid Corp. of the Philippines, a transmission company. Mindanao has suffered from outages for years as a third of supply comes from hydroelectric plants that are unreliable during dry season and subsidized electricity prices discourage constructing new plants. Summer temperatures are driving higher air-conditioning use.

The “Red Alert” warning means outages are to be expected in the two regions. On May 16, the Philippine capital Manila and nearby provinces under Manila Electric’s franchise experienced an hour of rotating power outages.

Aboitiz Power may spend about $5 billion building 2,000 megawatts of new capacity in the next five years, adding to its current portfolio of 2,300 megawatts, Aboitiz said in the interview. Profit in the three months ended March fell for the fifth straight quarter, down 9 percent to 4.2 billion pesos after revaluing its dollar loans and power sales declined. (BLOOMBERG)

http://www.mb.com.ph/power-supply-a-challenge-to-investors/

03 August 2012

SC stops Subic coal power plant project

The Supreme Court has issued a Writ of Kalikasan against the planned 600-megawatt coal-fired power plant of Redondo Peninsula Energy Inc. at the Subic Bay Freeport.

The high court in a July 31 ruling restrained the company from proceeding with the construction of the coal power plant after Party-list Rep. Teodoro Casiño complained against the expansion of the power plant complex from its original capacity of 300 MW.

RP Energy is a joint venture among Meralco PowerGen Corp., a unit of Manila Electric Co., and Therma Power Inc. of the Aboitiz Group and Taiwan Cogeneration International Corp. Meralco PowerGen owns a 50 percent plus two shares in the joint venture while Therma Power and Taiwan Cogeneration hold the balance.

The Supreme Court also remanded the case to the Court of Appeals for further hearings and judgment.

RP Energy said it was reviewing its legal options after the high court gave it 10 days to respond.

“We respect the process and are mindful of the rights of those who filed the petition. Although we cannot discuss the merits of the case, RP Energy reiterates its strong adherence to the laws that govern us in implementing the project such as the Department of Environment and Natural Resources’ ECC process,” RP Energy said.

“Our records show that we have not violated or reneged on our commitment to safeguard the environment and the communities around us,” it said.

RP Energy president Aaron Domingo earlier said the company was hoping to get the environmental clearance certificate for the second 300-MW unit of the 600-MW project by the fourth quarter. RP Energy aims to complete the coal project by 2015.

“We have advanced the development significantly. The site preparation is almost complete we’re actually mobilizing people already. The ECC is a underway,” Domingo said.

The proposed Subic project will utilize two 300-MW units utilizing the latest clean coal technology. The entire project is estimated to cost $1.28 billion.

Meralco, meanwhile, is pursuing an aero-derivative combined cycle power plant in Calamba, Laguna.

“We have secured the site. We have an ECC and we’re continuing multi-partite monitoring process. The site is available for putting up peaking capacity should Meralco need it,” he said.

Domingo said Meralco PowerGen is also looking at liquefied natural gas and coal projects with a capacity of 300 to 500 megawatts each. (Manila Standard Today)